For Krüger A/S, Aqvila are in the process of performing structural design of a standard “BioThelys™” MEGA skid to be used in connection with water treatment plants worldwide. The MEGA skid consists of 12 skids. Each skid will be equipped with all necessary mechanical and electrical installations in the workshop and then transported to its final destination, where the skids will be connected to each other in order to create the plug and play MEGA skid.

The standard MEGA skid is designed to withstand major loads from wind, earthquake and loads from land and sea transport.

More news

COLOPLAST, CMCR I 2018-08-15

COLOPLAST, CMCR I

Aqvila is hereby proud to announce that we have been awarded the full-service consultancy contract for the new Coloplast production facility, CMCR I, in Costa Rica.

Learn more COLOPLAST, CMCR I
SUND 3 TAKEOVER 2020-07-09

SUND 3 TAKEOVER

Aqvila is hereby proud to announce that Elfelagið SEV have successfully taken-over the new power plant (SUND3) in the Faroe Islands.

Learn more SUND 3 TAKEOVER
CMCR I PROGRESS 2020-08-25

CMCR I PROGRESS

The construction of Coloplast’s new production facility CMCR I in Cartago, Costa Rica, is well underway despite the COVID-19 pandemic and still planned to be taken over 2021 Q1.